“What does a charging station cost” is the most frequently asked — and worst answered — question in this sector. The answer depends entirely on what lies beneath: the station, installation, modifications to the meter cupboard, and additional smart functions.

The four cost components

1. The station itself. Range €600–€2,500 for AC stations, depending on brand, power, and smart functions. €600 is a basic station without an app, €2,500 is a top model with an app, RFID, monitoring, and PV integration.

2. The installation. €400–€1,200, depending on the distance between the meter cupboard and the station, type of wall mounting (pedestal or wall charger), and complexity of the cable run (digging or not, drill-throughs).

3. Potential meter cupboard modifications. €200–€1,500. Adding a residual current circuit breaker is inexpensive. Upgrading a group or switching from single-phase to three-phase can cost up to €1,500 or more (and must be done via grid operator Fluvius or ORES, with a lead time of 4–8 weeks).

4. Smart or additional functions. PV coupling, subscription to a management platform, dynamic load balancing — on average €100–€300/year or a one-time additional cost of €200–€500.

Example 1: standard residential installation

Single-phase, station next to meter cupboard, average station: €1,500–€1,800 all-in. This is the scenario for 60% of Belgian homes.

Example 2: standard residential installation with PV integration

Three-phase, smart station with solar integration, 8-meter cable run: €2,200–€2,800 all-in.

Example 3: more complex residential installation

Garage at the back of the garden, 25-meter cable trench, upgrading a group, smart station: €3,500–€4,800 all-in.

Example 4: SME with 6 charging points in the parking lot

Including load balancing, management platform, and backbone cabling: €18,000–€28,000 all-in. Per station, this amounts to €3,000–€4,700 — more than residential because infrastructure, monitoring, and grid management are included.

What to watch for in quotes

Three things that are typically hidden:

  1. “Starting from” prices that only cover the station without installation.
  2. Management platform subscription that begins after year 1.
  3. Grid connection cost via Fluvius or ORES (€0–€1,500 depending on the situation).

Always ask for a total all-in price, explicitly stating which costs are not included.

What is changing in 2026?

Subsidies for individuals have been significantly phased out compared to 2023–2024. For companies, investment deduction schemes for charging infrastructure at employee sites have been extended — have your accountant calculate this.