“We want 20 charging points, but our main connection is too small.” It is one of the most common questions during a site visit.
The good news: in many cases, a grid upgrade can be avoided. There are four technical solutions.
Four solutions without a grid upgrade
Dynamic load balancing
The main connection is monitored continuously. When the building draws a lot of power (HVAC, production, office lighting), the charging power drops automatically. At night or at weekends, when the building uses little, full power goes to the chargers. More in load balancing: what and why?
Peak shaving with a battery
A stationary battery of 50 to 250 kWh stores energy when it is cheap and releases it at peak moments. Especially interesting in combination with the capacity tariff: you do not buy the battery just to charge, but to lower your peak power.
Integration with solar panels
A rooftop PV installation produces during the day, when the cars are there. The charger prioritises solar energy and only then switches to grid power. When that combination pays off is covered in chargers with solar panels and a battery.
Phased rollout with load profiling
Instead of installing 20 charging points straight away, you install 8 with monitoring. After 3 months, you know exactly how much simultaneous charging power is needed.
When a grid upgrade is still needed
If all these solutions fall short, typically with more than 50 charging points, a DC fast charger and heavy industrial consumption, a grid upgrade is unavoidable.
Considering a fast charger? Read a fast charger on your business site: 50 kW or 200 kW first.
One partner, from measurement to management
Certipower installs, measures, manages and bills. On the company site, at the employee’s home and on the road, in one monthly invoice.
How many charging points can your site handle?
We measure your consumption profile and give you a concrete proposal.
- 14 days of measuring your consumption profile
- Solutions without a grid upgrade calculated
- A proposal with investment and savings in euros